Edition 3: November 2026
This edition covers producer prices through October 2026 for six construction-material groups, with five years of history behind each, and reports what changed since the second edition. It is written for anyone revisiting the material assumptions behind an estimate or weighing an explanation for a proposed increase. It reports market evidence. It does not estimate any contractor's cost and draws no conclusion about any contract.
The read
The metal products are still far above a year ago, and gypsum and concrete are still close to flat. In the producer price index, steel mill products are 32.9% above October 2025, copper wire and cable 25.5% and aluminum mill shapes 23.3%. Gypsum products (+0.9%) and ready-mix concrete (+2.4%) moved little over the same year, and the cement index is 0.4% lower. Softwood lumber is 10.6% above October 2025, but it is 10.2% below where it stood at the start of its five-year window.
Within October the six did not move together. Steel mill products rose 2.7%, the largest monthly increase among them. Copper wire and cable rose 0.6% and set another five-year high. Aluminum mill shapes rose 0.7% and gypsum products 0.6%. Ready-mix concrete slipped 0.1%. Softwood lumber fell 3.9%, its third monthly decline in a row. BLS marks all six October values preliminary, and they may be revised.
The raw metals parted from each other and, for aluminum, from the product. The benchmark price of raw aluminum fell 6.8% in October while the index for aluminum mill shapes rose 0.7%; raw copper was nearly unchanged (+0.2%) at a five-year high. These are different kinds of measure, and the notes below keep them apart.
A general claim that "materials are up" fits the three metal products in size (+32.9%, +25.5% and +23.3% over the year). Gypsum products (+0.9%) and ready-mix concrete (+2.4%) rose only slightly, and cement is 0.4% lower. For lumber it depends on the date it is measured from: +10.6% over one year, 10.2% below the start of its five-year window. Which part of an estimate any of this bears on depends on what the work is made of; the comparison table is arranged so that a reader can check the categories that matter to a particular estimate rather than a general claim.
The comparison
| Measure | Identifier | Latest period | Value | Month over month | Year over year | Source and status |
|---|---|---|---|---|---|---|
| Softwood lumber: PPI, softwood lumber | WPU0811 | Oct 2026 | 277.6 (index, 1982=100) | −3.9% | +10.6% | BLS PPI, preliminary |
| Copper: PPI, copper wire and cable | WPU10260314 | Oct 2026 | 610.0 (index, Dec 1986=100) | +0.6% | +25.5% | BLS PPI, preliminary |
| Steel: PPI, steel mill products | WPU1017 | Oct 2026 | 399.6 (index, 1982=100) | +2.7% | +32.9% | BLS PPI, preliminary |
| Aluminum: PPI, aluminum mill shapes | WPU102501 | Oct 2026 | 371.7 (index, 1982=100) | +0.7% | +23.3% | BLS PPI, preliminary |
| Gypsum products: PPI, gypsum products | WPU137 | Oct 2026 | 486.5 (index, 1982=100) | +0.6% | +0.9% | BLS PPI, preliminary |
| Ready-mix concrete: PPI, ready-mix concrete | WPU1333 | Oct 2026 | 394.8 (index, 1982=100) | −0.1% | +2.4% | BLS PPI, preliminary |
Context measures, each with its own latest period:
| Measure | Identifier | Latest period | Value | Month over month | Year over year | Source and status |
|---|---|---|---|---|---|---|
| PPI, cement (hydraulic) | WPU1322 | Oct 2026 | 356.4 (index, 1982=100) | +0.0% | −0.4% | BLS PPI, preliminary |
| PPI, gypsum building materials | WPU13710102 | Oct 2026 | 364.8 (index, Dec 1993=100) | +0.8% | −1.1% | BLS PPI, preliminary |
| LME copper, monthly average (USD per metric ton) | wb_copper_usd_mt | Oct 2026 | 14,508 | +0.2% | +35.1% | World Bank Pink Sheet, as published |
| LME aluminum, monthly average (USD per metric ton) | wb_aluminum_usd_mt | Oct 2026 | 3,061 | −6.8% | +9.6% | World Bank Pink Sheet, as published |
| Cement shipments, U.S. plants (metric tons) | usgs_cement_shipments_us_mt | Jul 2026 | 8,223,221 | −0.4% | +0.3% | USGS MIS, estimated |
| Housing starts, total, SAAR (thousands) | census_starts_total_saar | Sep 2026 | 1,221 | −5.2% | −7.4% | Census NRC, as published |
| Housing starts, single-family, SAAR (thousands) | census_starts_1unit_saar | Sep 2026 | 859 | −4.6% | +2.6% | Census NRC, as published |
Index levels are not comparable across rows; each series has its own base period. The rows do not all describe the same month: the price indexes and the metal benchmarks describe October, cement shipments July, and housing starts September. Two-year comparisons, against October 2024: lumber +6.6%; copper wire and cable +42.9%; steel +46.2%; aluminum mill shapes +55.6%; gypsum products +1.9%; ready-mix concrete +2.5%.
Historical charts
Each core index over 5 years, on its own scale, then the raw-metal benchmarks, then the six together rebased to a common start. Charts are drawn from series.csv; every value is in the table under each chart.
Values in this chart
| Period | PPI, softwood lumber |
|---|---|
| Nov 2021 | 309.0 |
| Dec 2021 | 384.5 |
| Jan 2022 | 480.6 |
| Feb 2022 | 504.8 |
| Mar 2022 | 540.7 |
| Apr 2022 | 443.7 |
| May 2022 | 453.3 |
| Jun 2022 | 337.4 |
| Jul 2022 | 337.8 |
| Aug 2022 | 326.0 |
| Sep 2022 | 309.1 |
| Oct 2022 | 303.0 |
| Nov 2022 | 299.4 |
| Dec 2022 | 282.7 |
| Jan 2023 | 268.0 |
| Feb 2023 | 277.2 |
| Mar 2023 | 274.3 |
| Apr 2023 | 271.2 |
| May 2023 | 270.9 |
| Jun 2023 | 267.4 |
| Jul 2023 | 279.4 |
| Aug 2023 | 266.6 |
| Sep 2023 | 262.0 |
| Oct 2023 | 253.5 |
| Nov 2023 | 240.8 |
| Dec 2023 | 241.4 |
| Jan 2024 | 244.3 |
| Feb 2024 | 247.9 |
| Mar 2024 | 255.8 |
| Apr 2024 | 258.2 |
| May 2024 | 248.9 |
| Jun 2024 | 247.3 |
| Jul 2024 | 242.8 |
| Aug 2024 | 249.9 |
| Sep 2024 | 256.2 |
| Oct 2024 | 260.4 |
| Nov 2024 | 269.3 |
| Dec 2024 | 272.4 |
| Jan 2025 | 267.5 |
| Feb 2025 | 274.9 |
| Mar 2025 | 288.0 |
| Apr 2025 | 280.4 |
| May 2025 | 271.5 |
| Jun 2025 | 266.3 |
| Jul 2025 | 261.4 |
| Aug 2025 | 263.7 |
| Sep 2025 | 252.8 |
| Oct 2025 | 251.0 |
| Nov 2025 | 251.4 |
| Dec 2025 | 250.1 |
| Jan 2026 | 260.0 |
| Feb 2026 | 270.3 |
| Mar 2026 | 268.3 |
| Apr 2026 | 282.9 |
| May 2026 | 284.5 |
| Jun 2026 | 282.5 |
| Jul 2026 | 300.5 |
| Aug 2026 | 294.5 |
| Sep 2026 | 288.8 |
| Oct 2026 | 277.6 |
Values in this chart
| Period | PPI, copper wire and cable |
|---|---|
| Nov 2021 | 411.8 |
| Dec 2021 | 402.5 |
| Jan 2022 | 405.0 |
| Feb 2022 | 409.0 |
| Mar 2022 | 416.2 |
| Apr 2022 | 425.9 |
| May 2022 | 419.8 |
| Jun 2022 | 405.2 |
| Jul 2022 | 387.7 |
| Aug 2022 | 367.0 |
| Sep 2022 | 367.8 |
| Oct 2022 | 366.3 |
| Nov 2022 | 376.1 |
| Dec 2022 | 381.1 |
| Jan 2023 | 399.4 |
| Feb 2023 | 408.9 |
| Mar 2023 | 404.2 |
| Apr 2023 | 401.4 |
| May 2023 | 383.1 |
| Jun 2023 | 384.5 |
| Jul 2023 | 385.7 |
| Aug 2023 | 384.2 |
| Sep 2023 | 381.1 |
| Oct 2023 | 377.1 |
| Nov 2023 | 378.3 |
| Dec 2023 | 383.9 |
| Jan 2024 | 385.6 |
| Feb 2024 | 389.2 |
| Mar 2024 | 393.2 |
| Apr 2024 | 416.1 |
| May 2024 | 458.5 |
| Jun 2024 | 451.3 |
| Jul 2024 | 433.3 |
| Aug 2024 | 414.0 |
| Sep 2024 | 415.2 |
| Oct 2024 | 427.0 |
| Nov 2024 | 419.1 |
| Dec 2024 | 413.0 |
| Jan 2025 | 417.4 |
| Feb 2025 | 424.9 |
| Mar 2025 | 450.7 |
| Apr 2025 | 472.7 |
| May 2025 | 459.2 |
| Jun 2025 | 467.0 |
| Jul 2025 | 490.2 |
| Aug 2025 | 473.5 |
| Sep 2025 | 464.5 |
| Oct 2025 | 486.1 |
| Nov 2025 | 486.9 |
| Dec 2025 | 510.8 |
| Jan 2026 | 530.9 |
| Feb 2026 | 537.9 |
| Mar 2026 | 536.8 |
| Apr 2026 | 533.8 |
| May 2026 | 564.9 |
| Jun 2026 | 577.2 |
| Jul 2026 | 578.7 |
| Aug 2026 | 601.8 |
| Sep 2026 | 606.5 |
| Oct 2026 | 610.0 |
Values in this chart
| Period | PPI, steel mill products |
|---|---|
| Nov 2021 | 448.7 |
| Dec 2021 | 449.7 |
| Jan 2022 | 441.5 |
| Feb 2022 | 400.1 |
| Mar 2022 | 376.6 |
| Apr 2022 | 386.7 |
| May 2022 | 427.4 |
| Jun 2022 | 420.2 |
| Jul 2022 | 404.1 |
| Aug 2022 | 384.9 |
| Sep 2022 | 357.6 |
| Oct 2022 | 337.2 |
| Nov 2022 | 326.7 |
| Dec 2022 | 315.6 |
| Jan 2023 | 308.0 |
| Feb 2023 | 315.3 |
| Mar 2023 | 318.2 |
| Apr 2023 | 329.7 |
| May 2023 | 347.2 |
| Jun 2023 | 345.8 |
| Jul 2023 | 329.4 |
| Aug 2023 | 322.9 |
| Sep 2023 | 311.5 |
| Oct 2023 | 304.1 |
| Nov 2023 | 298.0 |
| Dec 2023 | 305.1 |
| Jan 2024 | 321.4 |
| Feb 2024 | 332.5 |
| Mar 2024 | 305.7 |
| Apr 2024 | 297.6 |
| May 2024 | 298.6 |
| Jun 2024 | 293.3 |
| Jul 2024 | 283.1 |
| Aug 2024 | 275.3 |
| Sep 2024 | 271.0 |
| Oct 2024 | 273.4 |
| Nov 2024 | 278.3 |
| Dec 2024 | 266.5 |
| Jan 2025 | 261.6 |
| Feb 2025 | 268.9 |
| Mar 2025 | 287.4 |
| Apr 2025 | 303.8 |
| May 2025 | 326.7 |
| Jun 2025 | 309.2 |
| Jul 2025 | 305.5 |
| Aug 2025 | 308.8 |
| Sep 2025 | 304.6 |
| Oct 2025 | 300.7 |
| Nov 2025 | 291.6 |
| Dec 2025 | 312.4 |
| Jan 2026 | 315.4 |
| Feb 2026 | 325.1 |
| Mar 2026 | 331.4 |
| Apr 2026 | 341.6 |
| May 2026 | 350.0 |
| Jun 2026 | 359.9 |
| Jul 2026 | 374.7 |
| Aug 2026 | 381.2 |
| Sep 2026 | 389.1 |
| Oct 2026 | 399.6 |
Values in this chart
| Period | PPI, aluminum mill shapes |
|---|---|
| Nov 2021 | 258.9 |
| Dec 2021 | 244.0 |
| Jan 2022 | 253.8 |
| Feb 2022 | 271.4 |
| Mar 2022 | 278.2 |
| Apr 2022 | 287.6 |
| May 2022 | 278.6 |
| Jun 2022 | 262.3 |
| Jul 2022 | 251.0 |
| Aug 2022 | 242.1 |
| Sep 2022 | 238.8 |
| Oct 2022 | 231.7 |
| Nov 2022 | 228.2 |
| Dec 2022 | 231.1 |
| Jan 2023 | 236.3 |
| Feb 2023 | 240.3 |
| Mar 2023 | 240.4 |
| Apr 2023 | 236.0 |
| May 2023 | 237.0 |
| Jun 2023 | 234.7 |
| Jul 2023 | 231.7 |
| Aug 2023 | 230.9 |
| Sep 2023 | 228.8 |
| Oct 2023 | 227.9 |
| Nov 2023 | 227.6 |
| Dec 2023 | 226.8 |
| Jan 2024 | 225.1 |
| Feb 2024 | 225.5 |
| Mar 2024 | 224.4 |
| Apr 2024 | 225.7 |
| May 2024 | 235.6 |
| Jun 2024 | 241.1 |
| Jul 2024 | 242.4 |
| Aug 2024 | 237.1 |
| Sep 2024 | 235.1 |
| Oct 2024 | 238.8 |
| Nov 2024 | 244.7 |
| Dec 2024 | 246.6 |
| Jan 2025 | 246.9 |
| Feb 2025 | 249.6 |
| Mar 2025 | 262.1 |
| Apr 2025 | 266.7 |
| May 2025 | 257.1 |
| Jun 2025 | 256.7 |
| Jul 2025 | 276.1 |
| Aug 2025 | 291.3 |
| Sep 2025 | 295.9 |
| Oct 2025 | 301.5 |
| Nov 2025 | 312.0 |
| Dec 2025 | 320.6 |
| Jan 2026 | 328.7 |
| Feb 2026 | 349.4 |
| Mar 2026 | 353.2 |
| Apr 2026 | 367.8 |
| May 2026 | 385.1 |
| Jun 2026 | 392.7 |
| Jul 2026 | 386.3 |
| Aug 2026 | 369.3 |
| Sep 2026 | 369.2 |
| Oct 2026 | 371.7 |
Values in this chart
| Period | PPI, gypsum products |
|---|---|
| Nov 2021 | 397.2 |
| Dec 2021 | 398.0 |
| Jan 2022 | 417.5 |
| Feb 2022 | 415.2 |
| Mar 2022 | 421.7 |
| Apr 2022 | 422.2 |
| May 2022 | 445.5 |
| Jun 2022 | 448.1 |
| Jul 2022 | 449.2 |
| Aug 2022 | 461.3 |
| Sep 2022 | 462.7 |
| Oct 2022 | 461.3 |
| Nov 2022 | 463.0 |
| Dec 2022 | 462.4 |
| Jan 2023 | 462.2 |
| Feb 2023 | 466.7 |
| Mar 2023 | 469.5 |
| Apr 2023 | 465.1 |
| May 2023 | 460.9 |
| Jun 2023 | 460.0 |
| Jul 2023 | 459.0 |
| Aug 2023 | 458.1 |
| Sep 2023 | 455.9 |
| Oct 2023 | 455.9 |
| Nov 2023 | 455.6 |
| Dec 2023 | 454.8 |
| Jan 2024 | 454.8 |
| Feb 2024 | 464.4 |
| Mar 2024 | 471.9 |
| Apr 2024 | 468.6 |
| May 2024 | 477.0 |
| Jun 2024 | 477.0 |
| Jul 2024 | 477.3 |
| Aug 2024 | 477.1 |
| Sep 2024 | 477.9 |
| Oct 2024 | 477.3 |
| Nov 2024 | 479.9 |
| Dec 2024 | 480.5 |
| Jan 2025 | 479.8 |
| Feb 2025 | 485.5 |
| Mar 2025 | 487.4 |
| Apr 2025 | 485.1 |
| May 2025 | 483.9 |
| Jun 2025 | 483.7 |
| Jul 2025 | 483.4 |
| Aug 2025 | 484.0 |
| Sep 2025 | 482.1 |
| Oct 2025 | 482.3 |
| Nov 2025 | 480.8 |
| Dec 2025 | 480.2 |
| Jan 2026 | 480.3 |
| Feb 2026 | 480.7 |
| Mar 2026 | 479.5 |
| Apr 2026 | 480.4 |
| May 2026 | 475.1 |
| Jun 2026 | 477.5 |
| Jul 2026 | 481.6 |
| Aug 2026 | 481.6 |
| Sep 2026 | 483.4 |
| Oct 2026 | 486.5 |
Values in this chart
| Period | PPI, ready-mix concrete | PPI, cement (hydraulic) |
|---|---|---|
| Nov 2021 | 303.3 | 273.9 |
| Dec 2021 | 304.5 | 274.4 |
| Jan 2022 | 309.6 | 283.9 |
| Feb 2022 | 313.7 | 285.6 |
| Mar 2022 | 313.7 | 285.6 |
| Apr 2022 | 318.9 | 290.6 |
| May 2022 | 319.5 | 290.7 |
| Jun 2022 | 322.3 | 291.7 |
| Jul 2022 | 328.7 | 299.4 |
| Aug 2022 | 332.9 | 302.4 |
| Sep 2022 | 336.0 | 304.5 |
| Oct 2022 | 337.5 | 308.7 |
| Nov 2022 | 340.9 | 309.9 |
| Dec 2022 | 344.2 | 310.1 |
| Jan 2023 | 350.1 | 325.2 |
| Feb 2023 | 352.0 | 329.2 |
| Mar 2023 | 355.2 | 329.7 |
| Apr 2023 | 357.6 | 330.0 |
| May 2023 | 362.1 | 332.0 |
| Jun 2023 | 360.7 | 331.7 |
| Jul 2023 | 363.3 | 334.5 |
| Aug 2023 | 367.6 | 335.3 |
| Sep 2023 | 371.5 | 336.6 |
| Oct 2023 | 371.9 | 337.8 |
| Nov 2023 | 372.7 | 337.9 |
| Dec 2023 | 368.0 | 337.7 |
| Jan 2024 | 376.4 | 348.8 |
| Feb 2024 | 380.4 | 349.1 |
| Mar 2024 | 386.1 | 351.6 |
| Apr 2024 | 383.5 | 353.2 |
| May 2024 | 384.2 | 354.3 |
| Jun 2024 | 382.0 | 353.7 |
| Jul 2024 | 383.6 | 354.3 |
| Aug 2024 | 386.4 | 354.3 |
| Sep 2024 | 384.9 | 353.6 |
| Oct 2024 | 385.4 | 353.1 |
| Nov 2024 | 387.5 | 353.1 |
| Dec 2024 | 385.9 | 353.0 |
| Jan 2025 | 390.3 | 356.9 |
| Feb 2025 | 389.5 | 356.5 |
| Mar 2025 | 388.5 | 358.2 |
| Apr 2025 | 386.1 | 358.7 |
| May 2025 | 387.5 | 360.1 |
| Jun 2025 | 387.4 | 360.1 |
| Jul 2025 | 386.0 | 360.0 |
| Aug 2025 | 386.4 | 360.1 |
| Sep 2025 | 386.3 | 360.5 |
| Oct 2025 | 385.6 | 357.9 |
| Nov 2025 | 383.9 | 356.0 |
| Dec 2025 | 386.2 | 355.6 |
| Jan 2026 | 390.2 | 355.3 |
| Feb 2026 | 390.1 | 356.0 |
| Mar 2026 | 391.0 | 355.9 |
| Apr 2026 | 392.9 | 357.9 |
| May 2026 | 394.1 | 357.5 |
| Jun 2026 | 396.0 | 357.5 |
| Jul 2026 | 394.9 | 355.6 |
| Aug 2026 | 395.3 | 356.1 |
| Sep 2026 | 395.3 | 356.4 |
| Oct 2026 | 394.8 | 356.4 |
Values in this chart
| Period | LME copper, USD per metric ton |
|---|---|
| Nov 2021 | 9,729 |
| Dec 2021 | 9,551 |
| Jan 2022 | 9,782 |
| Feb 2022 | 9,943 |
| Mar 2022 | 10,231 |
| Apr 2022 | 10,161 |
| May 2022 | 9,377 |
| Jun 2022 | 9,024 |
| Jul 2022 | 7,545 |
| Aug 2022 | 7,982 |
| Sep 2022 | 7,746 |
| Oct 2022 | 7,651 |
| Nov 2022 | 8,050 |
| Dec 2022 | 8,375 |
| Jan 2023 | 9,038 |
| Feb 2023 | 8,937 |
| Mar 2023 | 8,856 |
| Apr 2023 | 8,809 |
| May 2023 | 8,217 |
| Jun 2023 | 8,397 |
| Jul 2023 | 8,477 |
| Aug 2023 | 8,349 |
| Sep 2023 | 8,277 |
| Oct 2023 | 7,937 |
| Nov 2023 | 8,190 |
| Dec 2023 | 8,400 |
| Jan 2024 | 8,339 |
| Feb 2024 | 8,305 |
| Mar 2024 | 8,689 |
| Apr 2024 | 9,464 |
| May 2024 | 10,139 |
| Jun 2024 | 9,648 |
| Jul 2024 | 9,385 |
| Aug 2024 | 8,972 |
| Sep 2024 | 9,237 |
| Oct 2024 | 9,534 |
| Nov 2024 | 9,076 |
| Dec 2024 | 8,916 |
| Jan 2025 | 8,991 |
| Feb 2025 | 9,331 |
| Mar 2025 | 9,740 |
| Apr 2025 | 9,177 |
| May 2025 | 9,533 |
| Jun 2025 | 9,835 |
| Jul 2025 | 9,771 |
| Aug 2025 | 9,670 |
| Sep 2025 | 9,984 |
| Oct 2025 | 10,740 |
| Nov 2025 | 10,812 |
| Dec 2025 | 11,785 |
| Jan 2026 | 13,012 |
| Feb 2026 | 12,951 |
| Mar 2026 | 12,529 |
| Apr 2026 | 12,951 |
| May 2026 | 13,543 |
| Jun 2026 | 13,552 |
| Jul 2026 | 13,543 |
| Aug 2026 | 14,326 |
| Sep 2026 | 14,474 |
| Oct 2026 | 14,508 |
Values in this chart
| Period | LME aluminum, USD per metric ton |
|---|---|
| Nov 2021 | 2,636 |
| Dec 2021 | 2,696 |
| Jan 2022 | 3,006 |
| Feb 2022 | 3,246 |
| Mar 2022 | 3,498 |
| Apr 2022 | 3,244 |
| May 2022 | 2,830 |
| Jun 2022 | 2,563 |
| Jul 2022 | 2,408 |
| Aug 2022 | 2,431 |
| Sep 2022 | 2,225 |
| Oct 2022 | 2,256 |
| Nov 2022 | 2,351 |
| Dec 2022 | 2,402 |
| Jan 2023 | 2,502 |
| Feb 2023 | 2,416 |
| Mar 2023 | 2,296 |
| Apr 2023 | 2,343 |
| May 2023 | 2,269 |
| Jun 2023 | 2,185 |
| Jul 2023 | 2,160 |
| Aug 2023 | 2,137 |
| Sep 2023 | 2,185 |
| Oct 2023 | 2,192 |
| Nov 2023 | 2,202 |
| Dec 2023 | 2,182 |
| Jan 2024 | 2,193 |
| Feb 2024 | 2,179 |
| Mar 2024 | 2,226 |
| Apr 2024 | 2,506 |
| May 2024 | 2,565 |
| Jun 2024 | 2,498 |
| Jul 2024 | 2,349 |
| Aug 2024 | 2,344 |
| Sep 2024 | 2,450 |
| Oct 2024 | 2,596 |
| Nov 2024 | 2,582 |
| Dec 2024 | 2,541 |
| Jan 2025 | 2,573 |
| Feb 2025 | 2,658 |
| Mar 2025 | 2,658 |
| Apr 2025 | 2,372 |
| May 2025 | 2,449 |
| Jun 2025 | 2,526 |
| Jul 2025 | 2,606 |
| Aug 2025 | 2,597 |
| Sep 2025 | 2,653 |
| Oct 2025 | 2,793 |
| Nov 2025 | 2,819 |
| Dec 2025 | 2,876 |
| Jan 2026 | 3,142 |
| Feb 2026 | 3,065 |
| Mar 2026 | 3,373 |
| Apr 2026 | 3,600 |
| May 2026 | 3,666 |
| Jun 2026 | 3,439 |
| Jul 2026 | 3,161 |
| Aug 2026 | 3,251 |
| Sep 2026 | 3,283 |
| Oct 2026 | 3,061 |
Values in this chart
| Period | Softwood lumber | Copper | Steel | Aluminum | Gypsum products | Ready-mix concrete |
|---|---|---|---|---|---|---|
| Nov 2021 | 100.0 | 100.0 | 100.0 | 100.0 | 100.0 | 100.0 |
| Dec 2021 | 124.4 | 97.7 | 100.2 | 94.3 | 100.2 | 100.4 |
| Jan 2022 | 155.6 | 98.3 | 98.4 | 98.1 | 105.1 | 102.1 |
| Feb 2022 | 163.4 | 99.3 | 89.2 | 104.9 | 104.5 | 103.4 |
| Mar 2022 | 175.0 | 101.1 | 83.9 | 107.5 | 106.2 | 103.4 |
| Apr 2022 | 143.6 | 103.4 | 86.2 | 111.1 | 106.3 | 105.1 |
| May 2022 | 146.7 | 101.9 | 95.2 | 107.6 | 112.2 | 105.3 |
| Jun 2022 | 109.2 | 98.4 | 93.6 | 101.3 | 112.8 | 106.3 |
| Jul 2022 | 109.3 | 94.1 | 90.1 | 97.0 | 113.1 | 108.4 |
| Aug 2022 | 105.5 | 89.1 | 85.8 | 93.5 | 116.1 | 109.8 |
| Sep 2022 | 100.0 | 89.3 | 79.7 | 92.3 | 116.5 | 110.8 |
| Oct 2022 | 98.1 | 88.9 | 75.1 | 89.5 | 116.1 | 111.3 |
| Nov 2022 | 96.9 | 91.3 | 72.8 | 88.1 | 116.6 | 112.4 |
| Dec 2022 | 91.5 | 92.5 | 70.3 | 89.3 | 116.4 | 113.5 |
| Jan 2023 | 86.7 | 97.0 | 68.6 | 91.3 | 116.4 | 115.4 |
| Feb 2023 | 89.7 | 99.3 | 70.3 | 92.8 | 117.5 | 116.0 |
| Mar 2023 | 88.8 | 98.1 | 70.9 | 92.9 | 118.2 | 117.1 |
| Apr 2023 | 87.8 | 97.5 | 73.5 | 91.2 | 117.1 | 117.9 |
| May 2023 | 87.7 | 93.0 | 77.4 | 91.5 | 116.0 | 119.4 |
| Jun 2023 | 86.5 | 93.4 | 77.1 | 90.7 | 115.8 | 118.9 |
| Jul 2023 | 90.4 | 93.7 | 73.4 | 89.5 | 115.6 | 119.8 |
| Aug 2023 | 86.3 | 93.3 | 72.0 | 89.2 | 115.3 | 121.2 |
| Sep 2023 | 84.8 | 92.6 | 69.4 | 88.4 | 114.8 | 122.5 |
| Oct 2023 | 82.0 | 91.6 | 67.8 | 88.0 | 114.8 | 122.6 |
| Nov 2023 | 77.9 | 91.9 | 66.4 | 87.9 | 114.7 | 122.9 |
| Dec 2023 | 78.1 | 93.2 | 68.0 | 87.6 | 114.5 | 121.3 |
| Jan 2024 | 79.1 | 93.6 | 71.6 | 87.0 | 114.5 | 124.1 |
| Feb 2024 | 80.2 | 94.5 | 74.1 | 87.1 | 116.9 | 125.4 |
| Mar 2024 | 82.8 | 95.5 | 68.1 | 86.7 | 118.8 | 127.3 |
| Apr 2024 | 83.6 | 101.1 | 66.3 | 87.2 | 118.0 | 126.4 |
| May 2024 | 80.6 | 111.3 | 66.5 | 91.0 | 120.1 | 126.7 |
| Jun 2024 | 80.0 | 109.6 | 65.4 | 93.1 | 120.1 | 125.9 |
| Jul 2024 | 78.6 | 105.2 | 63.1 | 93.7 | 120.2 | 126.4 |
| Aug 2024 | 80.9 | 100.5 | 61.3 | 91.6 | 120.1 | 127.4 |
| Sep 2024 | 82.9 | 100.8 | 60.4 | 90.8 | 120.3 | 126.9 |
| Oct 2024 | 84.3 | 103.7 | 60.9 | 92.3 | 120.2 | 127.0 |
| Nov 2024 | 87.2 | 101.8 | 62.0 | 94.5 | 120.8 | 127.7 |
| Dec 2024 | 88.2 | 100.3 | 59.4 | 95.3 | 121.0 | 127.2 |
| Jan 2025 | 86.6 | 101.4 | 58.3 | 95.4 | 120.8 | 128.7 |
| Feb 2025 | 89.0 | 103.2 | 59.9 | 96.4 | 122.2 | 128.4 |
| Mar 2025 | 93.2 | 109.4 | 64.0 | 101.2 | 122.7 | 128.1 |
| Apr 2025 | 90.8 | 114.8 | 67.7 | 103.0 | 122.1 | 127.3 |
| May 2025 | 87.9 | 111.5 | 72.8 | 99.3 | 121.8 | 127.7 |
| Jun 2025 | 86.2 | 113.4 | 68.9 | 99.2 | 121.8 | 127.7 |
| Jul 2025 | 84.6 | 119.0 | 68.1 | 106.7 | 121.7 | 127.2 |
| Aug 2025 | 85.3 | 115.0 | 68.8 | 112.5 | 121.9 | 127.4 |
| Sep 2025 | 81.8 | 112.8 | 67.9 | 114.3 | 121.4 | 127.3 |
| Oct 2025 | 81.2 | 118.0 | 67.0 | 116.5 | 121.4 | 127.1 |
| Nov 2025 | 81.4 | 118.2 | 65.0 | 120.5 | 121.0 | 126.6 |
| Dec 2025 | 81.0 | 124.0 | 69.6 | 123.8 | 120.9 | 127.3 |
| Jan 2026 | 84.1 | 128.9 | 70.3 | 127.0 | 120.9 | 128.6 |
| Feb 2026 | 87.5 | 130.6 | 72.4 | 135.0 | 121.0 | 128.6 |
| Mar 2026 | 86.8 | 130.3 | 73.8 | 136.4 | 120.7 | 128.9 |
| Apr 2026 | 91.5 | 129.6 | 76.1 | 142.1 | 120.9 | 129.5 |
| May 2026 | 92.1 | 137.2 | 78.0 | 148.7 | 119.6 | 129.9 |
| Jun 2026 | 91.4 | 140.2 | 80.2 | 151.7 | 120.2 | 130.5 |
| Jul 2026 | 97.3 | 140.5 | 83.5 | 149.2 | 121.3 | 130.2 |
| Aug 2026 | 95.3 | 146.1 | 85.0 | 142.7 | 121.2 | 130.3 |
| Sep 2026 | 93.5 | 147.3 | 86.7 | 142.6 | 121.7 | 130.3 |
| Oct 2026 | 89.8 | 148.1 | 89.1 | 143.6 | 122.5 | 130.2 |
Material notes
Standing notes on what each measure covers and what it is not are on the materials page and below the charts. What is new this month, by material:
Softwood lumber fell 3.9% in October, after declines in August and September, and is 11.0% above last December. Its year-over-year figure of 10.6% is measured against an October 2025 that was itself 3.6% below the October before, and the Octobers before that show +2.7%, −16.3% and +3.9%. The index is 10.2% below where it stood at the start of the five-year window, in November 2021, and far below its March 2022 peak of 540.7.
Copper wire and cable set another five-year high in October, at 610.0, and is 19.4% above December. The raw metal also set a five-year high: LME copper averaged 14,508 dollars per metric ton in October, 35.1% above a year ago. The product has risen less than the metal over the year, by 9.6 points (25.5% against 35.1%), a smaller gap than the second edition reported for September. In October the two moved by small amounts in the same direction, +0.6% for the product and +0.2% for the metal. Both yearly figures are lower than September's were; both levels are higher.
Steel mill products rose 2.7% in October and are 27.9% above December and 46.2% above October 2024. The yearly change of 32.9% is the largest among the six. The index is still 10.9% below where it stood at the start of the five-year window, under its December 2021 peak of 449.7, and has climbed from a January 2025 low of 261.6.
Aluminum mill shapes rose 0.7% in October to 371.7 and remain below the June high, which BLS has revised to 392.7. The raw metal moved the other way: LME aluminum averaged 3,061 dollars per metric ton in October, 6.8% below September's 3,283 and below its May high of 3,666. Its yearly change is +9.6%, because the October 2025 average it is measured against, 2,793 dollars, was lower still; a year-over-year rise and a one-month fall are both true of the same series. Over the year the product has risen more than the metal, +23.3% against +9.6%, a gap of 13.7 points, where the second edition found the two nearly equal for September. Over two years the product is up 55.6% and the metal 17.9%. The index measures what domestic producers receive for mill shapes and excludes imports; the LME figure is a world benchmark for unfabricated metal. The record shows that the two moved differently in October. It does not show why.
Gypsum products rose 0.6% in October to 486.5 and are 0.9% above October 2025. On the preliminary October figure, that is the highest level since the five-year high of 487.4 in March 2025, and below it. The narrower gypsum building materials index, which includes wallboard, rose 0.8% in the month and is 1.1% below a year ago, 2.0 points below the broader index's yearly change. BLS revised both gypsum indexes for September by more than any other series here; see Uncertainty.
Ready-mix concrete slipped 0.1% in October and is 2.4% above a year ago and 2.2% above December, just below its June five-year high of 396.0. The cement index was unchanged in the month and is 0.4% below a year ago; its five-year high was 360.5, in September 2025. Over the year, concrete's change exceeds cement's by 2.8 points. Cement is an input to concrete and the two indexes are separate measures.
Standing notes
What each measure covers, why it matters, and what it does not represent. These notes are the same in every edition; the paragraphs above say what is new.
What the measure covers. WPU0811 is the BLS producer price index for softwood lumber: what sawmills receive for dimension lumber, boards and timbers as they leave the mill, in index form with 1982 = 100, not seasonally adjusted. BLS builds it from lumber not edge worked and from softwood lumber made from purchased lumber, cut stock and dimension.
Why it matters. Framing is the largest single material line in most wood-frame residential work, and lumber is the most volatile of the six groups: within the past five years the index has risen and fallen by more than half within a year or two. A lumber claim needs a date attached to it more than any other.
What it is not. Not plywood, OSB, engineered wood, trusses or pressure-treated lumber, which BLS indexes separately. Not a delivered yard price, which adds freight, handling and dealer margin and moves on its own timing. Not a regional price; the index is national. A year-over-year figure for lumber can be large in either direction because the comparison month was itself unusual; the chart shows which.
What the measure covers. WPU10260314 is the BLS producer price index for copper wire and cable: what producers receive for building wire, power cable and similar manufactured products as they leave the plant, in index form with December 1986 = 100, not seasonally adjusted. Beside it, the edition reads the World Bank's monthly average of the LME copper settlement price (grade A cathode, U.S. dollars per metric ton), which is the raw metal.
Why it matters. Electrical work is priced largely on copper, and the raw metal is what moves in the news. The pair lets a reader see whether wire and cable followed the metal, lagged it, or moved by less, which is the usual pattern because fabrication, insulation and distribution costs sit between the two.
What it is not. The index is not copper plumbing tube, fittings, roofing copper or scrap. The LME price is a world benchmark in dollars per ton, not a U.S. delivered price, and it includes no fabrication. The gap between the two year-over-year figures is an observation about two series; it is not a margin, a markup or anyone's cost.
What the measure covers. WPU1017 is the BLS producer price index for steel mill products: what mills receive for sheet, plate, bars, structural shapes, pipe and tube and semifinished steel as they leave the mill, in index form with 1982 = 100, not seasonally adjusted. It is a broad group that BLS subdivides by product and by carbon, alloy and stainless grade.
Why it matters. Structural steel, rebar, decking, studs and pipe all begin as mill products, and mill pricing responds quickly to trade policy, energy costs and demand. Steel claims often cite a headline about tariffs; the index shows what mill prices did over the same months.
What it is not. Not fabricated or erected steel, not rebar installed, not hardware or fasteners, and not any one product: sheet and structural shapes can move differently within the group. Not a delivered price. The index does not say which product drove a month's change.
What the measure covers. WPU102501 is the BLS producer price index for aluminum mill shapes: what producers receive for sheet, plate, foil, extruded shapes and similar semifinished aluminum as it leaves the mill, in index form with 1982 = 100, not seasonally adjusted. Beside it, the edition reads the World Bank's monthly average of the LME aluminum settlement price (high-grade primary ingot, U.S. dollars per metric ton), the raw metal.
Why it matters. Windows, storefront, curtain wall, gutters, siding, flashing and much electrical and mechanical hardware are made from mill shapes. As with copper, the pair shows whether the manufactured product tracked the metal or moved on its own.
What it is not. Not finished products such as windows, doors or siding, which carry fabrication, glass, hardware and labor. The LME price is a world benchmark and not a U.S. delivered price; the regional premium that U.S. buyers pay above the LME price is not in either series. A gap between the two is not a cost.
What the measure covers. WPU137 is the BLS producer price index for gypsum products: wallboard and other gypsum building materials plus other gypsum products, in index form with 1982 = 100, not seasonally adjusted. Beside it, the edition reads WPU13710102, gypsum building materials (December 1993 = 100), the narrower index in which wallboard sits.
Why it matters. Drywall is in nearly every interior, and the index tends to hold within a narrow range for months and then move by several percent in one step, so a quiet stretch is not a guarantee about the next month.
What it is not. Neither index is the price of any one wallboard product, thickness or type, and neither includes installation, finishing or delivery. A broad gypsum-products index is not labeled here as the price of drywall. The two indexes have different base periods, so their levels are not comparable; their changes are.
What the measure covers. WPU1333 is the BLS producer price index for ready-mix concrete: what producers receive for concrete delivered from the plant, in index form with 1982 = 100, not seasonally adjusted. Beside it, the edition reads WPU1322, cement (hydraulic), the priced input, and the U.S. Geological Survey's monthly survey of portland and blended cement shipments from U.S. plants, in metric tons.
Why it matters. Foundations, slabs, sitework and most public work are priced on concrete, and the input and the product can move apart: aggregates, delivery, fuel and local plant competition sit between cement and a delivered yard of concrete. Cement shipments show whether the market behind a price move was busy or slack, several months after the fact.
What it is not. Cement is an input to concrete, not another name for it; the two indexes are kept apart. The concrete index is national; BLS also publishes regional ready-mix indexes, which are not read here. Not precast, block, aggregates or placement. Shipments are a volume, not a price, and USGS publishes them about four to five months after the month they describe, so they never describe the same month as the latest index value.
Context
What the evidence shows: for copper, the raw metal and the manufactured product rose in the same direction over the year, and the metal rose further. For aluminum, the product is further above a year ago than the metal is, and in October the metal fell while the product rose. Cement shipments from U.S. plants for January through July 2026 were 6.0% above the same months of 2025, a smaller margin than the second edition reported through June, and July alone was 0.3% above July 2025 and 0.4% below June. The housing-starts figures are the same ones the second edition carried: the Census workbook had not changed when this run was captured, so September is still the latest month. Total starts in September were 7.4% below a year earlier at a seasonally adjusted annual rate of 1,221 (thousands of units), 5.2% below August's 1,288, and 11.4% below December; the five-year low in the series was 1,182, in May 2026. Single-family starts were 2.6% above a year earlier at 859.
What the evidence does not show: why any of these moved. A higher raw-copper price is a plausible reason for a higher wire-and-cable index, and the timing is consistent with it, but the record does not establish that the one caused the other or how much of the product's rise the metal accounts for. The fall in raw aluminum beside a small rise in mill shapes is an observation about two series in one month; the record does not say whether the product index will follow the metal, and the gap between them is not a margin, a markup or anyone's cost. The record contains prices, not policy, and does not attribute the rise in steel. Cement shipments close to last July's level beside a cement index slightly below a year ago are two facts the record does not connect. Lower housing starts describe new residential units, not all construction.
What the evidence cannot connect: the shipments figure describes July, the starts figures September, and the price indexes October. The three-month gap between shipments and prices is the source's publishing lag, and no inference across it is made.
Uncertainty
The run flagged 14 items for the editor, and each is addressed here or above. Eight are preliminary values: the October figures for all six core indexes and for the cement and gypsum building materials indexes are marked preliminary by BLS and may be revised. BLS revises the most recent four months of a producer price index, so July through September are also still open.
Four are large yearly changes: steel mill products (+32.9%), copper wire and cable (+25.5%), aluminum mill shapes (+23.3%) and LME copper (+35.1%). Each was recalculated from the retained source file and matches. A yearly change depends on the month it starts from as much as on the latest month; the two-year figures and the charts show the longer path.
Two are large monthly changes. LME aluminum fell 6.8% from September to October; the figure was recalculated from the World Bank workbook and matches, and it stands beside a yearly change of +9.6% for the reason given in the aluminum note. The seasonally adjusted annual rate of total housing starts fell 5.2% from August to September. That flag repeats one raised for the second edition, because the Census workbook captured for this run is byte-for-byte the file captured in October; it is not a new decline. Census starts are survey estimates with wide sampling error and are revised.
BLS revised September, the month the second edition reported, for all eight indexes. Most changes were small. Under the revision rule in the methodology, three are noted because they move a comparison the second edition printed by half a point or more. Gypsum products for September is now 483.4, lower than the preliminary value; the second edition called that value a five-year high, and on the revised figures it was not, the high remaining March 2025. The revised September figure also shows a smaller monthly rise, and yearly and two-year changes each about a point smaller than printed. Gypsum building materials for September is now 362.0, also lower; the second edition reported it unchanged in the month and slightly below a year earlier, and the revised figures show a decline in the month and a larger shortfall from a year earlier. Aluminum mill shapes was revised down for June through September (September is now 369.2), which lowers the two-year comparison the second edition printed by slightly more than half a point. Revisions to lumber, copper wire and cable, steel, concrete and cement moved the printed comparisons by less than half a point. The revised September levels are in this edition's numbers.json as each series' prior-month value. The preliminary values they replace are in the second edition's numbers.json and in the BLS file retained for that edition, which is listed in that edition's evidence file and not in this one. The sizes of the changes described in this paragraph were worked out by comparing the two files and are stated in words. The second edition stands as published and is not changed by them. The World Bank, USGS and Census figures the second edition quoted are unchanged in this run's files.
The USGS shipments figures are marked estimated by USGS and are published about three to five months after the month they describe. The latest month in this record is July 2026. Shipments are strongly seasonal, so a change from December or from one month to the next says little on its own; the comparison with the same months of 2025 is the more useful one, and it relies on prior-year figures USGS may itself have revised. The five-year window for this series is limited to what the current workbook holds, and its chart shows 19 months, not 60.
The World Bank benchmark is a monthly average of daily exchange settlements in dollars per metric ton. It is a world price, not a U.S. delivered price, and it includes no regional premium or fabrication. A producer price index measures what domestic producers receive and excludes imports; it is not a delivered price or any supplier's cost. The gap between the metal and the product is an observation about two series, not a margin.
The edition page states which timestamp chain entry covers this edition's files and which authorities' tokens it holds. A timestamp shows the files existed unchanged by a date; it does not show that a source's figure was correct.
What the run flagged
The collection step flags conditions for the editor before the text is written: stale series, large moves, missing comparisons, preliminary values. They are listed as the run produced them.
| Flag | Series | Detail |
|---|---|---|
| PRELIMINARY | WPU0811 | 2026-10 is marked preliminary by the source and may be revised |
| LARGE_ANNUAL_MOVE | WPU10260314 | +25.5% year over year (2025-10 to 2026-10) |
| PRELIMINARY | WPU10260314 | 2026-10 is marked preliminary by the source and may be revised |
| LARGE_ANNUAL_MOVE | WPU1017 | +32.9% year over year (2025-10 to 2026-10) |
| PRELIMINARY | WPU1017 | 2026-10 is marked preliminary by the source and may be revised |
| LARGE_ANNUAL_MOVE | WPU102501 | +23.3% year over year (2025-10 to 2026-10) |
| PRELIMINARY | WPU102501 | 2026-10 is marked preliminary by the source and may be revised |
| PRELIMINARY | WPU137 | 2026-10 is marked preliminary by the source and may be revised |
| PRELIMINARY | WPU1333 | 2026-10 is marked preliminary by the source and may be revised |
| PRELIMINARY | WPU1322 | 2026-10 is marked preliminary by the source and may be revised |
| PRELIMINARY | WPU13710102 | 2026-10 is marked preliminary by the source and may be revised |
| LARGE_ANNUAL_MOVE | wb_copper_usd_mt | +35.1% year over year (2025-10 to 2026-10) |
| LARGE_MONTHLY_MOVE | wb_aluminum_usd_mt | -6.8% month over month (2026-09 to 2026-10) |
| LARGE_MONTHLY_MOVE | census_starts_total_saar | -5.2% month over month (2026-08 to 2026-09) |
The record
Four sources were fetched on November 13, 2026 and retained byte for byte: the BLS public API response for the eight PPI series (the request spans ten calendar years), the World Bank's monthly commodity workbook (marked updated November 3, 2026), the USGS cement workbook for July 2026, and the Census housing-starts time-series workbook, which is identical to the file retained for the second edition. Every figure above appears in numbers.json; the formulas are in dictionary.md; the rows the figures were computed from are in data.csv, and the charted windows are in series.csv. No correction has been made to this edition.
The next edition follows the BLS release of November producer prices; no retained file states that date. The World Bank's landing page, as captured for this run, gives December 2, 2026 for its next workbook update.
Suggested citation
Cite the edition and its version. If a later revision changes a figure, the revision is dated on this page and the original text stays visible. Field Assembly's text, tables and charts here are licensed CC BY 4.0; source files under evidence/ keep their publishers' terms. See Cite and reuse.
Download
- data.csvEvery indicator row in data run 2026-11-13T143010Z: 1692 rows, source-reported values at parsed precision, each with its source file and retrieval time
- series.csvThe 5-year window of each series as charted, with rebased values for the six core indexes
- measures.csvEvery figure the edition quotes, calculated measures marked
- dictionary.mdColumn definitions, units, formulas, revision policy, missing-value convention
- numbers.json · evidence.json · exceptions.json · issue.mdThe record as kept in the repository
The record behind this edition
Each retained file is the response as received, byte for byte, with its HTTP headers beside it and its SHA-256 in evidence.json. Methods and source list: methodology.
Retained source files (6)
- bls/ppi.jsonhttps://api.bls.gov/publicAPI/v1/timeseries/data/ · retrieved 2026-11-13T14:30:10Z · SHA-256 d16381f3db0b2cd4…
- worldbank_cmo/landing.htmlhttps://www.worldbank.org/en/research/commodity-markets · retrieved 2026-11-13T14:30:12Z · SHA-256 7ff3d360bf16ec15…
- worldbank_cmo/monthly_xlsx.xlsxhttps://thedocs.worldbank.org/en/doc/74e8be41ceb20fa0da750cda2f6b9e4e-0050012026/related/CMO-Historical-Data-Monthly.xlsx · retrieved 2026-11-13T14:30:15Z · SHA-256 3c8d9d8dbb48342f…
- usgs_cement_mis/landing.htmlhttps://www.usgs.gov/centers/national-minerals-information-center/cement-statistics-and-information · retrieved 2026-11-13T14:30:18Z · SHA-256 1fcc220b77bd31df…
- usgs_cement_mis/mis_xlsx.xlsxhttps://d9-wret.s3.us-west-2.amazonaws.com/assets/palladium/production/s3fs-public/media/files/mis-202607-cemen.xlsx · retrieved 2026-11-13T14:30:23Z · SHA-256 736aa02425efb44b…
- census_nrc_starts/starts_xlsx.xlsxhttps://www.census.gov/construction/nrc/xls/starts_cust.xlsx · retrieved 2026-11-13T14:30:26Z · SHA-256 a93609dae2df7674…
Timestamp record
Timestamp chain entry 2026-11-17T030736Z, 152 files, anchored 2026-11-17T03:07:36Z with RFC 3161 tokens from digicert, freetsa. An OpenTimestamps proof is stored alongside. Files: entry, manifest, tokens 2026-11-17T030736Z-digicert.tsr, 2026-11-17T030736Z-freetsa.tsr.
A timestamp shows that these files existed unchanged by that time. It does not show that a source's figure was correct.